VA Long Beach Health Care System

Long Beach, CA

Services

Activation

IOT&A

Outfitting

Transition Planning

Warehouse & Logisitics

Project Date

September 2017 - April 2022

Project Overview

GoE supported VA Long Beach Health Care System (VALBHCS) with multiple projects.

Project 402 – Outpatient Building 126 Seismic and Functional Renovation

In June 2017, GoE was awarded a contract to fully activate phase I of the outpatient building 126 within a six month-time frame. Phase I renovation included Patient Registration, Patient Education Classroom, Computer Lab, Main Hospital Lobby, and partial opening of the Specialty Care Clinic. In September of 2017, GoE was awarded a follow-on contract to support planning for the remaining phases of outpatient building 126 to include a Specialty Clinic and Audiology, Ophthalmology and Sleep Clinic. All phases of the outpatient building 126 renovation total approximately 88,000 SF.

 

Project 405 – Mental Health Inpatient/Outpatient Buildings & Community Living Center

In conjunction with outpatient building 126, GoE was awarded IOT&A planning for future major medical construction of three new buildings to include: Mental Health Inpatient (two-story, 40 beds and approximately 78,000 SF); Mental Health Outpatient (two-story and approximately 81,000 SF); and Community Living Center (multi-story, 120 bed living center and approximately 168,000 SF). Project 405 delivered LEED-Silver certified buildings that provide state-of-the-art facilities to care for Veterans who are elderly or have mental health requirements.

GoE continued support to VALBHCS throughout the A-E design and early construction planning phases with the following services:

  • Project team meeting facilitation
  • Inventory assessment and reuse analysis
  • Medical equipment and furniture cut sheet development
  • Interior design with medical equipment & furniture room lay-in(s)
  • 3D room renderings
  • Equipment and procurement package planning
  • Design review support (operational and mechanical, electrical and plumbing – MEP review)
  • Planning for operational activation and relocation
  • Planning for furnishing and equipment installation and testing
  • Logistics and warehouse support
  • Integrated master schedule development/coordinate design and construction with IOT&A